| Report
To Holiday Hideaway Homeowners Association Regarding
Status
Of The Holiday Hideaway Water System
May,
2003
PURPOSE:
Provide a factual report on an independent review of the Guemes Island
Water Company’s System (System). The review considered several key
aspects of the System, including; 1) Regulatory Compliance, 2) Operations
and Maintenance Considerations, 3) Status of Improvements and Capital
Financing and 4) Future Capital Needs. This report was intended to be
a factual review of issues, and was not intended to include a “pro
and con” comparison of acquisition of the System by the property
owners versus Skagit PUD. The acquisition discussion should occur amongst
the affected property owners, based upon a review of facts as well as
opinions on what is in the “best interest” of individual owners
and the overall community.
The review was conducted
by Mark Spahr, a retired water system manager and professional engineer,
including 30 years experience with water system operations, management
and engineering. The review included contacts with the State Department
of Health (DOH), County Health Department (CHD), State Department of Ecology
(DOE), Public Works Trust Board (PWB) of the State Department of Community
Trade and Economic Development and State Utilities and Transportation
Commission (UTC). In addition, all System facilities were visited and
planning/engineering documents were reviewed.
1. REGULATORY
COMPLIANCE: Currently, the System is subject to regulation by
three state agencies, DOH, DOE and UTC. DOH is responsible for design
standards and review/approval, operations and maintenance and drinking
water quality. DOE reviews and issues water rights which include provisions
relative to sea-water intrusion. As a “for-profit” corporation,
the System is also subject to regulation by the UTC relative to its water
rates and “rate of return on investment” or profit. If the
Homeowner’s Water Association were to assume ownership of the System,
the UTC would not be involved since it would be operated as a “non-profit”
corporation.
DOH Status:
The System has a “Green” operating permit from DOH which means
the System is in compliance with all health-related water quality sampling
and water quality regulations, that it is operated by a state-certified
operator and that required planning is up-to-date and approved (including
an engineering plan, wellhead protection and sea-water intrusion plans
and studies).
The System’s
wells contain levels of dissolved iron and manganese which exceed DOH’s
“secondary” standards, however secondary standards relate
to “aesthetic” issues (fixture and laundry staining), which
do not directly affect human health. DOH recently approved (March 18,
2003) the use of Well 4, and with that DOH has approved the System to
serve up to 217 residential and 50 recreational service connections (an
increase of 42 connections, since the System was previously approved for
175 residential and 50 recreational service connections).
DOH regulations have
the most direct impact on day-to-day operations, maintenance, water quality
sampling and design/construction of new or replacement facilities. These
regulations would continue in effect regardless of future ownership.
DOE Status:
DOE has issued water rights for the System which include specific “sea-water
intrusion” conditions which include; 1) Wells 3, 4, 5 be equipped
with automatic shutoff equipment that would turn the wells off if water
level in the wells declines to within 0.5 feet above sea level, 2) test
for chloride and conductivity and static water level quarterly, submitting
results annually to DOE (which has been done), 3) if pumping of the wells
causes “. . . chloride concentrations to show an increasing trend
in any of the wells, immediate action shall be required . . . actions
include, but are not limited to reducing the . . . withdrawal rate . .
. lowering the annual quantity removed from the wells, rotating pumping
cycles, or turning off certain wells. . . If corrective measures fail
to prevent chloride concentrations from staying at or below 35 mg/L, the
water right holder shall relinquish the option to perfect additional allocated
quantities regardless of the stage of development.” and 4) Complete
construction of a 100,000+ gallon storage tank prior to March 1, 2017
(the added storage would allow peak demands to be met during “3-day”
summer weekends without having to “over-pump” the wells, thus
minimizing the threat of sea-water intrusion).
In addition, DOE requires
metering of all water sources to insure that withdrawals are in conformance
with water rights. These requirements would continue regardless of ownership.
Note: Since water rights are “real property”, ownership of
the water rights must be transferred as part of any ownership transfer.
UTC Status:
The UTC regulates “for profit” utilities such as the Guemes
Island Water Company (GIWC) to insure that service rates are reasonable
and justified. In March 2000 an average rate increase of 44% was approved
to cover the cost of system operations and a $5 monthly surcharge was
approved to partially finance the cost of capital improvements discussed
in Section 3 of this report. In addition the system generates revenue
from new connections through a “Facilities Charge” of $4,500
for all new connections and a service connection charge of $620 (these
fees were instituted in 1994). The UTC would not be involved if a non-profit
water association was formed which gave all customers a voice in establishing
future rates and policies. Likewise, the UTC would not be involved if
a public agency such as the PUD were to assume ownership.
2. OPERATIONS
AND MAINTENANCE CONSIDERATIONS: The current System has five wells
(four of which have been approved by DOH and are equipped for service).
Wells 1 and 2 have a combined output of approximately 27 gallons per minute
(gpm), and wells 3, 4 (and 5 which has been drilled but not tested, equipped
or approved) will have a combined output of approximately 35.5 gpm (total
water rights equal 62.5 gpm). Wells 3, 4 and 5 have concentrations of
iron and manganese that exceed DOH standards, which can lead to staining
of laundry and plumbing fixtures. All active wells pump water into the
distribution system to meet customer demands and fill two 44,000 reservoirs
which have an overflow elevation estimated at 235 feet above sea level.
The distribution system is composed of approximately 3,600 feet of 2-inch,
19,000 feet of 4-inch and 800 feet of 6-inch PVC mains, including approximately
40 distribution system valves, three fire hydrants and a dozen “blow-offs”.
The 2 and 4-inch pipe are “glue-joint” PVC which was constructed
in two phases, the first phase was constructed in ---- (-- years old),
the second phase was constructed in 1978 (25 years old), while the 6-inch
pipe was constructed in 1994 (9 years old).
An automated control
system has been recently installed to monitor and control wells 1-4, including
recording the amount of water pumped from each. In addition, the water
levels in wells 3 and 4 are continuously monitored and controls would
turn off these wells if the water level drops to within 0.5 feet above
sea level. The control system also starts and stops the wells based on
the amount of water in the reservoirs, and it is designed to prevent the
well pumps from running more than 16 hours per day, to minimize impact
on the aquifer and to prevent sea-water intrusion.
A number of lots in
the service area are at, near or above the elevation of the existing reservoirs,
thus a booster pump station is needed to increase pressure to a “pressure
zone” within a portion of Block 3. However, the booster pump station
does not have the capacity to provide service for other “higher
elevation” lots in Blocks 2, 3, 6 and 7, hence several dozen lots
have “static” pressures of between 24 and 33 pounds per square
inch (psi) (these pressures are calculated based on topographic maps,
actual pressures may vary and will be verified by measurements in coming
weeks). During periods of peak demand, water pressure in certain areas
is reported to drop below the DOH-required minimum 20 psi as a result
of “head losses” resulting from increased water flow (optimal
water pressure should be between 40 and 80 psi).
There is no standby
generator at the booster pump station, hence during extended power outages,
lots served by that facility may be out of water. However recent electrical
improvements have included a “plug” and a “transfer
switch” to accept power from a future generator.
For its size (currently
serving approximately 120 customers), the System is relatively complex.
Routine maintenance should consist of a daily review of the automated
control system including troubleshooting of any alarm or “out of
bounds” conditions, a weekly visit to each pumping facility (including
seasonal clearing brush and mowing as needed), monthly collection of required
bacteriological sample(s), quarterly sampling for chloride and specific
conductance (required by DOE), quarterly checks of the reservoirs to verify
security and sanitation, annual “exercising” of distribution
system valves, hydrants and blow-offs, periodic (every 2-3 years) “flushing”
of mains to clear internal deposits (such as iron and manganese oxide),
and occasional (every 5 to 7 years) pressure washing and cleaning of the
interior of reservoirs. In addition the system should be monitored quarterly
to evaluate whether leakage is a problem (comparing the total amount of
water pumped to the amount of water sold through customer meters, current
records indicate that leakage is not a problem), and develop on-going
“trending” to track water pumped from wells (to identify unusual
or unexplained increases in the amount of water pumped). It is estimated
that this routine work could be accomplished with an average of 5 hours
per week. As treatment for iron and manganese removal is added in the
future, additional routine maintenance and testing will be required.
The status of proposed
capital improvements to address deficiencies and enhance the System’s
capabilities is discussed in Section 3.
3. STATUS
OF IMPROVEMENTS AND CAPITAL FINANCING: The System’s capital
improvement plan had the following overall goals:
- Resolve all low
water pressure problems, including during peak demands
- Provide water treatment
for iron and manganese removal
- Enhance and automate
management and control of the System, aimed at protecting the groundwater
resource from sea-water intrusion
- Increase the System’s
capacity to serve more customers
- Enhance fire protection
in some areas.
A loan application
in the amount of $243,476 was approved by the State PWB in 1999, which
included a scope of work to accomplish these goals through the following
efforts; a) perform aquifer tests on Wells 3, 4 and 5, b) acquire DOE’s
approval of water right applications for change (approving withdrawal
of a total of 62.5 gpm from all 5 wells), c) construct iron/manganese
water treatment for Wells 3, 4 and 5, d) construct a 105,000 gallon reservoir,
e) construct a new pump station to deliver water from the new reservoir
to the existing reservoirs and distribution system, f) upgrade the existing
booster pump station at the existing reservoirs, including increased capacity
and distribution system improvements to resolve low pressure problems
throughout the System, g) install an automated communication and control
(telemetry) system and h) complete water system and wellhead protection
plans.
For a variety of reasons,
the GIWC project manager’s estimate was not sufficient to accomplish
the original scope of work. The work actually completed includes; a) aquifer
test on Wells 3 and 4, b) awaiting approval from DOE regarding water right
changes, c) constructed building to house telemetry and the future pump
station and water treatment, d) constructed piping for future reservoir,
pump station and water treatment, and d) telemetry installed to all existing
sites (except Well 5, new reservoir and water treatment), e) upgraded
existing booster pump station (but it does not have sufficient capacity
to resolve low pressure problems beyond the existing pressure zone), f)
completed comprehensive plan, sea-water intrusion study and well head
protection plan, g) obtained approvals to use well 4 (March 2003).
On March 20, 2001,
the GIWC requested that the scope of work for their PWB loan be changed
from the original scope to only those improvements that had “been
completed to date”. Both DOH and the PWB approved the change, and
the project has been deemed “complete” (without the ability
to use Well 5 and deletion of the 105,000 gallon storage reservoir, water
treatment, pump station or improvements to enhance pressure). To date,
GIWC has made 3 principal payments on the loan, totaling $31,663.32, leaving
a balance of $211,813.12 at 5% interest. The next payment is due October
1, 2003 in the amount of $23,828.98 (principal and interest).
The Loan Agreement
includes a provision that the PWB “reserves the right to demand
payment in full of the outstanding principal balance of the loan”
if there is any change in ownership of the System. The HOA has submitted
a Financial Capacity analysis to the PWB, using anticipated income and
expenditures (based on current rates and applicable GIWC expenditures).
If the PWB deems that the HOA is financially viable, the loan would be
transferred to the HOA. The PWB would have no concern over acquisition
by PUD.
The GIWC project manager’s
estimate (dated 3/15/01) to complete the original project’s scope
of work is $209,955 (including testing and equipping Well 5, new reservoir,
pump station and water treatment – no inclusion of measures to address
low pressure problems) . As part of this study, several cost items were
independently verified, and it appears that the current cost of completion
is more like $250,000 (which will continue to increase with time).
Of the original five
goals, only two have been completely accomplished:
- Approval of Well
4 has resulted in the System’s capacity being increased to serve
an additional 42 residential customers (from 175 to 217).
- Provision of the
telemetry system enhanced the ability to manage and protect the ground
water resource from sea-water intrusion.
Partial progress was
made towards other goals:
- A building was
constructed to house the telemetry system, and the future water treatment
and pump station
- Piping was installed
for the future reservoir, water treatment and pump station
- Wellhead Protection,
Sea-Water Intrusion and Comprehensive Planning were completed and approved
- DOE authorized
revisions to water rights as requested
The Loan Agreement
and Promissory Note includes 5% interest and the term is for 20 years,
expiring in October 2018. Terms call for an annual payment of 1/20th of
the principle ($12,173.80) plus interest on the declining balance. The
GIWC has pledged their accounts receivable (revenue from customers) as
the collateral for repayment of the loan.
Currently, the PWB
has money to loan at 1% interest for projects. The 1% interest rate was
not available in 1998-99 and can not be refinanced at the current rate.
4. FUTURE
CAPITAL NEEDS: In addition to the cost of completing the identified
capital improvements, investment in the existing distribution system should
not be overlooked. The system consists of “glue-joint” PVC
pipe which has a finite serviceable life (estimated in the range of 40
to 50 years). The service life of such a system could be significantly
shortened through modifying (raising) service pressure even by as little
as 15 psi. Currently the distribution appears to be in good condition
(as indicated by a very low rate of leakage).
Much of the System
was constructed in 19--, which means that the system is approach an age
where prudent financial planning should anticipate systematic replacement.
Replacement could be phased over a number of years (for example, replacing
2,500 feet every third year). The cost of replacement (using higher quality
PVC pipe) would depend on a number of factors, but for planning purposes
a replacement cost of $45 per lineal foot is reasonable (annually adjusted
for inflation). Hence replacement of 2,500 feet of main would cost an
estimated $112,500.
5. SUMMARY:
The GIWC’s water system appears to be in good condition and is in
compliance with applicable DOH, DOE and UTC requirements. Recent expenditures
by GIWC have resulted in approval of planning documents, full utilization
of water rights, an automated monitoring, updating the booster pump for
the upper pressure zone, an automated control system, and capacity for
an additional 42 residential connections. In addition, partial progress
was made towards future construction of a new reservoir, pump station
and water treatment; however completion of these projects has been estimated
at approximately $250,000. In addition, the issue of low service pressure
during peak demands needs further evaluation and planning for eventual
replacement of pipeline facilities should be considered. |